| I-01 | Viaduct structural and operational clearance | Control-centre modules ↔ rail asset owner / viaduct | What surveyed geometry, movements, operational envelope and maintenance access constrain the proposal? | Survey, engineering assessment and an agreed asset-protection/approval route. |
| I-02 | Rail-borne vibration | Modules, occupants and equipment ↔ rail vibration source | What exposure and equipment sensitivity must be assessed, and would mitigation be needed? | Measurement or justified model, agreed performance criteria and a checked mitigation proposal. |
| I-03 | Canal navigation and flood interface | Candidate crossings ↔ canal owner / relevant waterway authorities | What span, level, support locations and temporary works would preserve required navigation, flood performance and access? | Survey, hydraulic and structural assessments, and the relevant permissions identified with responsible parties. |
| I-04 | Road crossing and access | Candidate links ↔ road owner / highway authority | What crossing geometry, loading, vehicle protection, access and construction arrangements are acceptable? | Assessed crossing/access proposal and confirmation of applicable rights and approvals; no specific legal instrument is assumed. |
| I-05 | Foundations near canal banks | Candidate foundations ↔ ground / canal bank | How would loads and construction affect bank stability, water and maintenance access? | Ground investigation, foundation and temporary-works assessment, and agreed monitoring/acceptance criteria. |
| I-06 | Overhead electrical line | Buildings, plant and construction equipment ↔ line operator | What operating and construction envelopes, electrical effects and access requirements apply to this asset? | Operator asset data, site-specific electrical and construction assessment, and the necessary operator agreement. |
| I-07 | Historic mine workings | Existing and proposed foundations / utilities ↔ workings and ground | Where are the workings, what is their condition, and how might loads, excavation or treatment affect stability? | Records and investigation, ground-risk assessment, justified exclusions/treatment and identification of required rights or consents. |
| I-08 | Utility services corridor | Non-signalling infrastructure ↔ utility owners / operators | Which services, capacities, separations, routes and access arrangements are required? | Service requirements, coordinated route study, engineering design and ownership/interface agreements. |
| I-09 | Non-signalling ↔ signalling systems | Infrastructure services ↔ signalling equipment and system owner | What power, communications, environmental, electromagnetic compatibility and resilience requirements cross the boundary? | Jointly developed interface requirements, allocated responsibilities and a verification plan. |