Offshore‑Wind Maintenance Lens with “Doping” Constraints Hornsea Two demo

Input = forecast sea‑state (significant wave height). Output = turbine‑visit visibility through a 3‑hour weather window. This is a self‑contained toy model you can re‑wire and extend.
← Back to apps index Explainer level
Synthetic weather. Edits are temporary in this tab; refreshing restores the preset. Export downloads a result file; importing accepts weather only, not a saved plan.

Outputs

–
Tasks scheduled within their allowed intervals
–
Average delay from earliest start (hours)
–
Crew visit occupancy of forecast horizon (excluding cooldown)

Sea‑state forecast (Hs)

Line = wave height. Shading = feasible 3‑hour start times for the selected doping level. Markers = task windows.
Hs (significant wave height) feasible 3‑hour start task window

Schedule result

For each task: earliest feasible 3‑hour slot inside its interval, given its doping constraints and the chosen policy.
Task Status Chosen start (UTC) Delay (h) Notes

Progress trajectories

This chart shows the “building going up”: cumulative tasks completed over time.
These are the two computed policy trajectories, not all feasible trajectories or a proof of optimality. Each step occurs when a whole visit finishes.
FIFO policy Opportunistic policy
Tip: Edit the doping thresholds and watch the feasible windows change. Then swap the policy to see alternate trajectories.